Cyprus could lose almost half of its conventional power generation capacity from early 2030, parliament members warned on Thursday, with House President Annita Demetriou asking “what will we tell people” when it happens.
Cyprus is obliged to retire polluting generators at the Dhekelia and Vasilikos power stations at the end of 2029. The ageing steam boilers at Dhekelia alone have a rated capacity of 360 megawatts. If the European Union also requires units 1, 2 and 3 at Vasilikos to be withdrawn, the loss will reach or exceed 700 megawatts, out of the roughly 1,400 megawatts the Electricity Authority of Cyprus (EAC) can in theory generate from oil today.
Demetriou, who also leads DISY, spoke at the end of the plenary debate. She expressed deep concern at what had been said in the chamber, and warned that losing half of the EAC’s generating capacity in 2030 would have tragic consequences for the public.
The debate, on an issue AKEL had put on the agenda titled ‘Delays in critical energy projects and the risks to the economy, the country’s energy security and consumers’, covered all the open energy issues. These included the unfinished natural gas terminal, high electricity charges and the electricity interconnection between Cyprus and Greece. But it focused on the risk to generating capacity.
Cost warnings
AKEL general secretary Stefanos Stefanou accused the government of making worse the energy chaos it had inherited from the Anastasiades administration. He said AKEL had been warning since 2022 of the coming adequacy problems, and of the need to replace the polluting units in good time, but had not been listened to.
Stefanou said the Christodoulides government had been very late in activating the capacity mechanism, which the law provides for to find extra generation urgently. He warned that the mechanism would sharply increase the cost of producing a kilowatt-hour. Citing estimates by technical experts, he said that cost could exceed 40 cents, from just over 30 cents today.
DISY parliament member Nikos Georgiou, who chairs the House Energy Committee, said reserve capacity had to be found urgently to avoid difficult situations, but that securing it through a capacity mechanism would be very expensive for consumers. He pointed to Ireland, which paid almost 1.5 billion euros when it used a capacity mechanism and bought extra generation through tenders.
DIKO parliament member Chrysis Pantelides called on President Nikos Christodoulides to find solutions, describing the shortfall as a national issue. He said only three years remained to do what was needed before the old Dhekelia units are withdrawn at the end of 2029. His DIKO colleague Adamos Aspris said Cyprus risked hitting an iceberg of inadequate generation while many people engaged in pointless discussion, as the crew of the Titanic had done.
Storage
Speakers noted that storage systems due to be installed in the next one to two years could boost output at peak times. But almost all of them stressed that, at this stage, storage cannot make up for the lost generation, unless the loss is avoided through a request to the EU for a new extension of the compliance deadline.
Background
A study by the Cyprus Energy Regulatory Authority (CERA), reported by Phileleftheros in September, projected a 720-megawatt shortfall in 2030 under its worst-case scenario. In that scenario, natural gas does not arrive, the interconnection does not operate and conventional EAC units are withdrawn.
Energy Minister Michalis Damianos said in October that two new 80-megawatt generating units are planned at Dhekelia by the end of 2029. Eight companies are being assessed for the contract to complete the liquefied natural gas terminal at Vasilikos, which the Natural Gas Public Company (DEFA) aims to award before summer 2027.