Limassol begins €9.2 million project to replace 100 kilometres of water network

Relevant News

The Limassol District Local Government Organisation (EOA Limassol) has started work on replacing 100 kilometres of water supply network in the centre of the city, in a project with a budget of €9.2 million that is co-financed by the European Union.

The project began with a ceremony on Thursday, 6 August 2026, and covers sections of the existing network that are ageing, have recorded a high number of failures and show high levels of water losses.

The new drinking water distribution network will cover around 220 roads and serve about 40,000 residents across an area of approximately 2.6 square kilometres. The works include installing new water supply pipes made from modern materials, excavation and backfilling, as well as restoring roads and pavements after the works are completed.

Pam00133 1536x849

EOA Limassol president Giannis Tsouloftas said the project upgrades, modernises and strengthens the city’s water infrastructure. He added that the construction of the project would improve citizens’ daily lives and quality of life while supporting Limassol’s modernisation efforts.

The project area extends from the Enaerios area along Makariou III Avenue to the Central Fire Station; from the Central Fire Station along the Garillis riverbed to Yildiz Street in the Four Lanterns area; from Four Lanterns along Yildiz, Navarinou, Irinis, 16 June and Gladstonos streets to Pentadromos; and from Pentadromos along Anexartisias Street towards the seafront avenue.

EOA Limassol said the completed project is expected to reduce failures and water losses and, as a result, reduce interruptions to water supply for consumers. It added that the project will also reduce operating and maintenance costs, improve services and contribute to ensuring better drinking water quality.

The project forms part of the organisation’s wider planning for water supply, sewerage, flood protection, renewable energy and recycled water production infrastructure.

As part of this wider planning, works are also under way for the installation of 80,000 smart water meters worth €13 million, as well as the construction of four new water reservoirs with a total capacity of around 9,000 cubic metres and a budget of €3.8 million.

Contract 10/2025 was signed on 2 June 2026 between EOA Limassol and contractor An. Christou Properties & Constructions Limited. The project is co-financed by the EU Cohesion Fund through the THALIA 2021-2027 Programme, and construction works are expected to last 24 months.

“The project is implemented under the Cohesion Policy Programme THALIA 2021-2027 with co-financing from the EU.”

Untitled Design 37 1536x864

Follow en.philenews on Google News and be the first to know all the news about Cyprus and the world.