Section of Nicosia’s Digenis Akritas Avenue to close for 28 weeks

Relevant News

The Nicosia District Local Government Organisation (DLGO) will close part of Digenis Akritas Avenue, between Kallipoleos and Larnakos avenues, in phases from Monday, October 5. The closure will allow it to repair, maintain and strengthen the stormwater culvert beneath the avenue.

All phases of the project will take 28 weeks, provided work goes smoothly and without delays. The first phase, from Protagorou Street to Alkamenous Street, is expected to be completed on December 4, 2026. The project costs 2,259,499 euros plus VAT. The state is funding two-thirds of the cost and the DLGO the rest, through stormwater fees paid by property owners.

The avenue is used by residents of Pallouriotissa and Kaimakli, as well as by many other drivers leaving Nicosia via Kallipoleos Avenue since Makarios Avenue was made one-way.

Traffic arrangements

Because the work will take place underneath the avenue, the section of road above it will be closed for the safety of workers and road users.

In the first phase, one lane towards Larnakos Avenue will close first, followed later by both lanes. Details of each later phase will be announced before it starts, and full information on the project is on the DLGO’s website. The DLGO apologised for any inconvenience and asked residents, business owners and road users for their understanding.

Why the work is needed

The reinforced concrete culvert was built about 50 years ago, when the Kotsirkas river was covered over, to carry rain and river water beneath one of Nicosia’s busiest avenues.

According to the DLGO, it has worn and corroded over the decades through the natural ageing of materials, constant vibration, the weight of vehicles and heavy traffic, combined with the river water. The damage is worst under junctions with main roads and on stretches used constantly by lorries.

The DLGO said the project is of major importance, both for draining stormwater and for the safety of vehicles and pedestrians. It identified the problem when it took over responsibility for stormwater management. It then made the project a priority, giving particular weight to the safety of vehicles passing over the culvert every day.

The works

The work involves opening sections of the roof slab for access and ventilation, cleaning the culvert and temporarily supporting its roof. The walls and roof will then be strengthened with new reinforcement and sprayed concrete, and the joints repaired. Finally, the openings will be covered and the road surface restored.

The DLGO aims to use its annual income from stormwater fees, about two million euros a year, to tackle key problem spots in Nicosia district every year, so that conditions improve each year and the risk of flooding falls.