The renovation of Tseriou Avenue in Nicosia, Cyprus, is facing additional delays, extending the disruption for residents and businesses, officials told the House Transport Committee on Thursday.
Eleftherios Eleftheriou, Director of the Public Works Department, said the contractor has requested a 114-day extension due to issues with storm drains and utility services.
The 23 million euro project, which began in February 2023 with a 30-month timeline, is now expected to be completed by late 2025, with the Hippocrates Street section finished by March 2025.
The project, currently 40% complete, spans 6.5 km and includes two lanes in each direction, green spaces, pavements, and cycle paths.
A second phase of the project, from Theoktistos roundabout to Strovolos Avenue, is set to commence on 14 October. Stavros Stavrinides, Mayor of Strovolos, detailed the three-phase plan for this 2.2 km stretch, which will include wide pavements, 530 tree beds, 275 parking spaces, and 18 pedestrian crossings and bus stops.
Residents along Tseriou Avenue expressed frustration over the delays and ongoing disruptions. They cited issues such as traffic congestion, dust pollution, and safety concerns, particularly regarding emergency vehicle access.
In response to these concerns, residents have requested a postponement of the new works scheduled for October, stricter completion timelines, and improved traffic management plans.
However, municipal officials stated that delaying the project’s start is not feasible due to potential additional costs and contractor compensation claims.