Chaos is expected to prevail on Tseriou Avenue if the reconstruction works start in May, given that approximately 25,000 drivers will seek alternative routes such as Strovolos Avenue, which accommodates about 40,000 vehicles, while problems are also expected on the neighboring Constantinopolis and Kantara Avenues, which are also used by thousands of drivers.
However, Strovolos Mayor Mr. Andreas Papacharalambous stated before the Parliamentary Committee on Interior Affairs that Tseriou Avenue will continue to be used even after the commencement of the works.
It is noted that both MPs and municipal groups attending the session emphasized the need to set timelines for the start and completion of the works, citing the fact that timelines set in the past have been overturned due to changes in the design, which was ultimately assigned to a private consultant.
Furthermore, the Auditor General became involved following complaints regarding the tender process.
According to the complaints, while the private consultant estimated the project cost at €7.7 million, it was ultimately found to cost €8.5 million.
The Audit Service will examine whether the initial offer was indeed revised and whether this was done based on established procedures or if there is an element of arbitrariness involved.
If indeed a deviation from the initial estimate is found, responsibility will be investigated.
Only two bids were submitted for the implementation of the Tseriou Avenue project, with one having a slight deviation from the other, leading to a complaint to the Audit Service to investigate whether this is coincidental or if there is anything suspicious.
The tenders were announced in June 2023, and construction works were scheduled to begin around the end of November or early December of the same year.
It seems that the implementation of the project cannot start immediately due to objective reasons.
Specifically, among other things, the alienation of dozens of properties or parts thereof is pending, as without alienation, the contractor who will undertake the project cannot arbitrarily enter foreign properties.
The Municipality stated before the Committee that it is a matter of days for the alienation or even expropriation process, where deemed necessary, to be initiated so that work can begin with the contractor to whom the bid will be awarded.
However, the Audit Service believes that the bid should not be awarded unless technical and other issues are clarified, so as not to observe the phenomenon of budget burden due to delays.
The President of the Committee, Aristos Damianou, stated that based on the data, the budget amounts to €10.2 million without considering the cost of alienations.