Larnaca’s revamped Ermou Street opens a month early for Christmas (video)

Relevant News

Shopkeepers on Larnaca’s Ermou Street can breathe easier after regeneration works finished a month ahead of schedule, with the town’s busiest commercial road set to reopen to vehicles next Wednesday.

Larnaca Mayor Andreas Vyras announced the early completion during a site visit on Friday morning, saying the street would be decorated for Christmas before reopening.

Philenews visited the site and captured images and video of the radically transformed commercial street, which bears no resemblance to its previous condition. Mastic and lentisk trees have already been planted along the road, LED lighting has been installed, and planters, modern street furniture and colourful canopies will be added soon.

On the downside, part of the new Gladstonos Square will open to vehicles following objections from some shopkeepers, and the decorative floor pattern at the start of Ermou Street differs from the rest because that section falls under the separate Alkis and Acropolis squares regeneration project.

Despite this, the transformation marks a genuine change for an area that has seen many shops close in recent years. Hopes now rest on the project bringing more people to the centre and filling long-vacant premises.

Works completed early

Vyras said the section at the start of Ermou and Gladstonos Square had been scheduled for completion on 15 December. However, in coordination with the contractor, they finished earlier.

51574e8ab0585c6908595dfa4cce8f15

“The street will be decorated for Christmas and will open on Wednesday for vehicles. We’re confident this will help the commercial centre, especially with the holidays approaching,” he added, noting it was a difficult project.

“But upgrading the commercial centre was unavoidable. There’s been disruption for shopkeepers and the public, but I believe without this project there would be no prospect for the commercial centre.”

5812d9ed27d28ae36808b5f58293199f

Wider regeneration timeline

The mayor said the commercial centre regeneration project overall has justified delays of four to five months, mainly due to the EAC’s ageing network. The electricity authority has deployed additional crews working overtime, according to Vyras.

E53969f1b693d549b6fb3c39afe58923

Works for the centre’s regeneration currently continue on Zinonos Street and are expected to finish up to the Atrium Zenon hotel by November 2026. The overall project will be completed in spring 2027.

8fe7c4e0d6bc3c4bd28a0ed2e408021a

Regarding the Alkis and Acropolis squares regeneration works, these currently continue on the busy Grigori Afxentiou Avenue and are expected to finish by July 2026.

2a1a5d7c77bd411d096cd454fd34c25f