Akamas road works expected to restart in February

Relevant News

A tender for the first phase of the road network in the Akamas National Forest Park was launched on 6 November 2026, with work suspended since December 2023 expected to restart in February 2027. The contract has an estimated value of 5.63 million euros (6.694 million euros including VAT). The work is expected to take 13 months, with completion targeted for 28 February 2028. Bids are due on 8 December 2026 and will be opened the same day in the presence of the relevant evaluation committees.

The project is part of the Sustainable Development Plan for the park, which receives more than 400,000 visitors. Since the suspension, the unfinished road network has had maintenance, drainage and safety problems, and full implementation of the park’s management measures has been delayed. The project is a precondition for the park to work in practice as a protection tool, with controlled access, park rangers, safe movement of visitors and the ability to respond quickly to fires.

Three roads and a car park

Phase A focuses on improving three key roads with a total length of about 9.9 kilometres. Road 1A, from Aspros Potamos to Toxeftra and Lara, is about 6.2 kilometres long and is the main route to the Lara coast. Road 2, the Lara ring road, is about 2.7 kilometres long and is designed to ease traffic around the turtle protection area. Road 4Bi, from Toxeftra to Avakas, is about 1.0 kilometre long and leads to the entrance of the Avakas gorge.

The phase also includes an organised car park in the Lara area, which aims to curb uncontrolled parking on sensitive ecosystems and to organise visitors before they enter the park’s zones of absolute protection. Work is subject to seasonal bans to protect turtle nesting and bird breeding.

The wider plan aims to protect the park’s biodiversity by managing visitor numbers, with a defined road network, limits on uncontrolled access, organised visitor facilities, alternative ways of getting around and environmental monitoring.

Sixty per cent of the cost is covered by the THALIA 2021-2027 Cohesion Policy Programme and the remaining 40 per cent by national funds. Because of the EU funding, the project will face additional oversight beyond the contracting authority’s own financial control. The Treasury will verify spending and certify it to the EU. The Intermediate Body, the Control Directorate of the Ministry of Transport, Communications and Works, will oversee the physical delivery of the contract.

Suspension and breaches

After the main environmental assessments were completed in 2021, work on Phase A began on 27 October 2022 and was due to finish on 27 December 2023. Problems that arose during construction led to its suspension on 11 December 2023, with 17.67 per cent of the work completed and 94 per cent of the time elapsed.

As early as October 2023, environmental organisations had reported what they described as very serious breaches of legally binding terms of the project’s environmental approval. The organisations were Terra Cypria, BirdLife Cyprus, the Cyprus Wildlife Society, the Initiative for the Rescue of Natural Coasts and the Federation of Environmental Organisations of Cyprus. Their representatives took part in the assessment of the park’s Sustainable Development Plan and in the work of the ad hoc committee on the appropriate assessment and the environmental impact assessment committee.

After the suspension, the design was changed to reduce its environmental footprint and to meet additional technical and environmental requirements. Following cabinet decisions on 20 December 2023 and 11 March 2024, a design with fewer interventions was taken forward. A supplementary appropriate assessment report followed in 2024 and a compliance report from the environmental authority in 2025. A revised design with stronger environmental safeguards is now being implemented.

Payments for Phase A were made on the basis of invoices and certifications. The dispute with the contractor was resolved through an amicable settlement, with the involvement of the Law Office of the Republic and the approval of the Finance Ministry.

All phases by late 2028

Work on all phases and infrastructure is due to be completed by 15 November 2028, with a 12-month defects liability period.

For Phase A, including the Lara car park, the modified construction drawings were approved on 31 July 2026. On 30 September 2026 the Intermediate Body asked for the technical terms to be revised and for the environmental terms to be made contractual.

A tender for information and recreation facilities (hubs) was launched on 24 August 2026 and has received one bid, which the Department of Forests is evaluating. A previous tender in 2022, with a revised estimate of 6.59 million euros, was cancelled because only one bid was submitted, at 8.9 million euros, above the revised estimate.

Work on the Baths of Aphrodite to Fontana Amorosa forest road, costing 160,000 euros, began on 9 November 2026 with earthworks expected to take about three weeks, and safety barriers are due by mid-December. The road has significant safety problems, and the work is mainly intended to ensure safe access for fire engines and other emergency vehicles.

Among the remaining work, Phase B, which includes the study for Lara to Agios Minas, runs from 1 November 2026 to 15 November 2028, with Aspros Potamos to Mountiko and Koutsagkas to Tzifin due by 2027. Phase C work is scheduled from 1 January to 1 August 2028, irregular access points will be closed off between 1 August and 30 September 2028, and habitat restoration will follow Phase A. A final hydrological and hydraulic study for Avakas to Toxeftra, delivered on 16 October 2026, is being evaluated.