The Tenders Review Authority has decided to approve the request from ICT Logicom Solutions for temporary measures to prevent the Cyprus Electricity Authority (AΗΚ) from proceeding with the evaluation of bids and the awarding of contracts under the new competition for smart meters.
The decision was based on the following considerations:
It concurred with AΗΚ that this is an important project and noted that “the significance and the urgency of its implementation have not been disputed by the Applicants (ICT). We also agree with the Contracting Authority that there is a need to implement the project within the set timeframes.”
However, it added the following: “We do not agree, however, that the time required to complete the procedure before us, including the Applicants’ declaration for an expedited hearing, will lead the project off schedule, risking the loss of funding.” The Regulatory Authority scheduled a hearing on December 12 to address the substance of ICT’s appeal.
Responding to AΗΚ’s position that the public interest demands the rapid advancement of the competition, the Regulatory Authority commented as follows: “Without overlooking that the project should commence as soon as possible to avoid the risk of funding loss (from the EU Recovery and Resilience Fund), we must also seriously consider that co-financed public tenders, such as the present competition with an estimated cost of €35 million, must be governed by legality to minimize the risk of compensations being paid, which can be achieved as long as there is a possibility to rectify irregularities, namely during the initial stage of the competition announcement.”
The decision to accept the request for temporary (prohibitory) measures was agreed upon by the Chair of the Tenders Review Authority, Efi Papadopoulou, and members Loizos Kappas and Dimos Thoma. Member George Anastasiou disagreed and issued a different, dissenting decision.
Among other things, in his decision, Mr. Anastasiou included the following: “Both the risk of losing substantial funding from the EU Recovery and Resilience Fund and the significant contribution of new meters to the reduction of emissions, as explained to us during the hearing, leave me with no doubt that the tendering process should proceed as quickly as possible.
In contrast, I could not perceive objective damages that the applicants (ICT) might incur due to the non-issuance of a temporary measure, especially when they will have the opportunity, if they wish, to lodge an appeal against the decision of the Contracting Authority after the processing of observations/questions or after the final decision on the contract award.”