The Electricity Authority of Cyprus (EAC) has extended to 28 February 2027 the deadline for net metering applicants to submit the forms and technical plans needed to have their electrical installations inspected, it said in an announcement.
The original deadline was 27 November 2026. The EAC said it granted the extension in response to requests from customers and associations.
Under the EAC’s new decision, inspection and connection of the photovoltaic system must be completed by 14 May 2027. Applicants must submit their forms and electrical plansby 28 February at the latest for this to be possible.
The extension applies only to those who applied to join net metering by 31 December 2025, the last day applications were accepted, even if they had not yet installed their photovoltaic system. Anyone who applied after that date falls under net billing, which has replaced net metering.
The flexibility given to those applicants does not mean they can stay under the old scheme indefinitely while delaying the installation and operation of their home photovoltaic systems, whether because their home is not finished or for any other reason. Instead, they must meet set deadlines to keep their right to remain on net metering.
The new arrangement effectively gives applicants about a year and a half from the application cut-off to connect their systems. Those who applied in time but have not completed the procedures must act within the new deadlines, or lose the option of connecting under the old scheme.
How the two schemes differ
The main difference between the two lies in how the energy a household produces is offset against what it consumes.
Under net metering, the electricity produced is offset against the electricity consumed, calculated in kilowatt-hours. Under net billing, the offset is based on the monetary value of the energy produced compared with the cost of the electricity drawn from the grid.
The change affects the benefit to consumers and can lengthen the time it takes for their investment to pay for itself.