More than half of Cyprus-Greece interconnector cable now manufactured
More than half the subsea cable needed for the Great Sea Interconnector (GSI) linking Cyprus and Greece has been manufactured, with 510 of the 900 kilometres required for the Cyprus-Crete link now complete. The figures come from the latest progress report received by the Cyprus Energy Regulatory Authority (CERA) from Greeceās Independent Power Transmission Operator … Continue reading More than half of Cyprus-Greece interconnector cable now manufactured